Rick Johns, construction project manager for design, construction and space management, is retiring after serving Missouri S&T for 23 years. His last day is Tuesday, Jan. 3.
Read More »The Library Exterior Renovation is doing well and proceeding on schedule. The contractors will be erecting overhead protection at the main entrance as the work proceeds to the south side. The main entrance will remain open throughout the project. Please be cautious and follow signage to avoid the work areas. If you have any questions […]
Read More »The exterior renovation to Curtis Laws Wilson Library is proceeding on schedule. The contractors built overhead protection at the main entrance as the work proceeds to the south side. The main entrance will remain open throughout the project.
Read More »The exterior renovation to Curtis Laws Wilson Library is proceeding on schedule. The contractors will build overhead protection at the main entrance as the work proceeds to the south side. The main entrance will remain open throughout the project.
Read More »The sidewalks on the east and west side of the Curtis Laws Wilson Library will be temporary closed during certain construction activities to renovate the library’s exterior. Please be careful and observe safety barricades.
Read More »A construction project is underway to renovate the exterior of the Curtis Laws Wilson Library. The project will include installing a new roof, replacing damaged brick, cleaning and restoring all exterior walls, adding new foundation drainage on the north and east walls, and replacing third-floor study room windows. For more information, please contact Rick Johns, […]
Read More »The sidewalk between McNutt Hall and the Computer Science Building has been closed for crews to add a new water line. The sidewalk will be closed for approximately two weeks.
Read More »The Computer Science Building will experience a hot water outage 8 a.m.-3 p.m. tomorrow (Thursday, Sept. 19). The building may feel slightly cooler.
Read More »To install a new air compressor, compressed air will not be available in the Engineering Research Laboratory 10 a.m.-3 p.m. Wednesday, Aug. 28.
Read More »The cooling system at S&T’s Engineering Research Laboratory (ERL) will be affected Wednesday, Aug. 14, and until noon Thursday, Aug. 15. There will be no air conditioning in ERL during this time.
Read More »