The last well for the geothermal energy system project was drilled in Lot 36 on Oct. 18. Paving has been completed in Lot 8 and circuit piping in Lot 36 will continue until its completion in mid-November. Lot 36 is ahead of schedule and is anticipated to be back in service near the end of December, weather permitting. Lot 11 is scheduled to be back in service by the third week of November. The primary goal for the next two months is to complete all geothermal piping and have Parking Lots 11 and 36 back in service before winter.